SH25 Kopu Bridge Replacement
Location: Kopu, Thames-Coromandel District & Hauraki District
Dates: July 2009 - completed by mid 2012
Details:
- new two-lane bridge, approximately 580m long, with a cycle/walkway
-
the bridge will be 12.95m wide with 3.5m wide traffic lanes and 1.2m shoulders
-
construction of approximately 2.5 km of approach roads, including a new link road to SH26 east of the bridge
- new four-leg roundabout at the junction of SH25 and SH26.
- associated drainage, signage, barriers, roadmarkings, landscaping and other ancillary works
- services relocations including watermains, and sewer pipes
- widening of SH26 north of the SH25/26 junction to include a flush median and wide left hand shoulder
- Cultural design features, including:
- 10 Pou
- Waka etching
- Water etching and design on handrails and concrete barriers
- Patiki etching
- Ureia (Taniwha) bridge Pepeha
Client: New Zealand Transport Agency
Project Scope Diagram
June 2010

May 2010


March 2010

|
|
 |
|
|
| |