FLEMINGTON STAGE 14

The development at Flemington has continued with the latest stage (Stage 14) being completed. Having commenced in late September 2016, HEB Construction has completed the building of 53 numbered lots and one medium density section. This has involved moving over 24,000 cubic metres of material during the earthworks stage and completing 1400 metres of new kerb, 5500m2 of new road and all associated sewer, stormwater, water, power and communications services.

The final surface layer was completed in early March, two weeks ahead of the programmed schedule.

The next stage (Stage 5) commenced in late February with a planned completion of May 2017.